Northgate Transit Center Park & Ride Changes

As early as December 5, 2016, crews will begin building a new driveway for the Northgate Park & Ride (west) on NE 103rd Street, adjacent to First Ave NE. Driveway construction is expected to take two days to complete, weather permitting. This driveway is needed to accommodate the next phase of Sound Transit’s construction changes coming to the Northgate Transit Center Park & Ride.

In this new configuration, drivers will enter the Northgate Park & Ride (west) from the driveway on NE 103rd Street and exit from the driveway on NE 100th Street.

Upcoming construction of the Northgate light rail station will occupy additional space in the Northgate Park & Ride (west) as indicated on the map. Fencing will go up as early as December 7 around the middle section of the west lot. To replace the loss of those stalls a new replacement park-and-ride will open on the west side of First Ave NE between NE 100th and 103rd Streets. This new, North Seattle Park & Ride, has 102 new stalls and is expected to open as early as December 5, 2016.

Northgate Park & Ride Changes Mapphase-2-change-map

For more information:

Visit http://www.soundtransit.org/northgatestation/northgate-transit-center-park-and-ride

Contact Andrea Burnett, Sound Transit Community Outreach at 206-398-5300 or andrea.burnett@soundtransit.org

For issues that need immediate attention after normal business hours, call Sound Transit’s 24-hour construction hotline at 888-298-2395

multilingual-text

Changes coming to Northgate Transit Center Park-and-Ride

As early as Monday, October 10, 2016 a new interim park-and-ride lot (Lot B) will open across the street from the Northgate Transit Center at the southeast corner of NE 100th Street and First Avenue NE. The new interim lot is needed to replace stalls that will be unavailable after the Northgate Link light rail station construction begins later this fall.

Construction will occupy the west side of the Northgate Transit Center Park-and-Ride along First Avenue NE. The park-and-ride entrance on NE 100th Street will stay open at this time.

The capacity of the existing interim park-and-ride lot (Lot A) at the corner of NE 103rd Street and Fifth Ave NE will be reduced as Northgate Mall resumes exclusive use of some stalls.

As construction of the station progresses, we’ll keep you informed about additional changes to the park-and-ride.

For more information:

 

Map of Phase 1 Changes

  • 20160920-northgate-link-extension-parking-phase1